Delivering a coordinated mechanical installation for a pharmaceutical laboratory expansion
Working alongside BES Ltd, our team delivered a new mechanical package as part of the expansion of Perrigo Pharmaceuticals’ existing laboratory facility in Braunton, Devon. Spanning a 12-week programme, the aim was to improve the layout and workflow of the facility.
The project involved fitting a Variable Refrigerant Flow (VRF) system, alongside associated refrigerant pipework, condensate drainage and ceiling-mounted cassette units. Each component required careful consideration to ensure it was correctly positioned and integrated within the expanded space.
A key challenge was managing the mechanical services around the building structure without interrupting other trades working on site. Particular attention was given to the routing of refrigerant pipework and condensate drainage, ensuring these could be compatible alongside the wider building services without compromising the installation or the available space.
The ceiling-mounted cassette units also required detailed planning. Each needed to align with the ceiling grid while allowing sufficient space for the other services located above it. Achieving the required positioning involved close liaison with the wider project team to resolve potential clashes and ensure a well-integrated final result.
With several contractors working concurrently on site, regular communication was essential throughout the programme. We worked closely with BES Ltd and the other trades to manage interface requirements, agree installation arrangements and address any challenges as they arose.
The project was successfully delivered within the agreed 12-week timeframe, providing Perrigo Pharmaceuticals with the mechanical services needed to support its expanded laboratory.
Ben McDarmaid, director at MIG Mechanical, highlighted the importance of coordination and teamwork throughout the project: